Often, yes. The City of Southlake's Fence Guidelines require a permit for a fence over 7 feet high, any fence used as a pool barrier, any fence with brick or stone columns, and masonry 48 inches or more from the bottom of the footing. You apply online. Plan on a scaled site plan, a fence elevation and, for masonry, a sealed engineered design.

In this guide

  1. Do I need a permit for a fence in Southlake?
  2. How tall can a fence be in Southlake?
  3. What drawings and site-plan details does Southlake ask for?
  4. How do I apply for a Southlake fence permit, step by step?
  5. Can I build a modern horizontal fence in Southlake?
  6. What do brick or stone columns add to the permit?
  7. What does a pool barrier fence need in Southlake?
  8. Does my HOA have to approve the fence, and what about subdivision walls and main roads?
  9. What if my design does not fit the rules?
  10. How does Southlake compare with Colleyville and Westlake, and how do we handle it?

Need this done? See masonry fencing.

Southlake does not handle fences the way Dallas does, and the city's own documents do not all say the same thing. A plain 6-foot cedar fence in a back yard may need no city permit at all, while a short stone column at the driveway does. This guide follows the rules in the order you will meet them, each tied to the city document it comes from.

We are Park Cities Fence & Deck, a fence company serving Southlake. We prepare the drawings and file the permit for the fences, columns and gates we build. The steps below work whether you hire us, hire someone else or apply yourself. Rules change, so treat this as general information and confirm your case with Building Inspections before you build.

Do I need a permit for a fence in Southlake?

It depends on the height, the material and what the fence does. Two city documents answer the question, and they do not match. The Fence Guidelines from Building Inspections, dated February 2026, list six cases. The handout "When is a building permit required?", dated May 2026, lists a different set for residential fences.

Both agree on the core: over 7 feet, masonry and pool barriers need a permit. Only the guidelines name brick or stone columns. Only the handout names front yards, subdivision fences and floodplains. The handout itself says it is best to call and ask before installing a fence, and we agree. The Building Inspections number printed on both documents is 817-748-8236.

When a Southlake fence needs a permit, according to each city document
Your fenceFence Guidelines (February 2026)"When is a building permit required?" (May 2026)
Taller than 7 feetPermit requiredPermit required
Any part of a pool barrierPermit requiredPermit required
Brick or stone columnsPermit requiredNot listed by name
Masonry fencePermit required at 48 inches or more from the bottom of the footingListed as masonry; engineered plans required
In a front yardNot listedPermit required
Subdivision fenceMust conform to zoning, including materialPermit required
In a floodplainNot listedPermit required

What this means for you: If your fence appears in either column, treat it as needing a permit until Building Inspections tells you otherwise. A wood or iron fence 7 feet or shorter, in a side or rear yard, with no columns and no pool behind it, is the case neither list names.

How tall can a fence be in Southlake?

Eight feet is the general limit. Section 39.1 of Zoning Ordinance No. 480 allows fences, walls and hedges in any required yard as long as they do not exceed 8 feet in height. The permit line sits lower, at 7 feet, so a 7.5-foot privacy fence is allowed by zoning and still needs a permit.

The Fence Guidelines add two more numbers. A perimeter fence over 8 feet requires a variance from the Zoning Board of Adjustment. A fence in the rear yard that stands at least 10 feet inside the property line may be up to 14 feet before a variance is required. The city's multi-purpose court checklist uses the same idea: a court fence over 8 feet tall must sit at least 10 feet from the side and rear property lines.

The front yard is where the documents go quiet. Section 39 gives no separate front yard height, and the ordinance counts anything over 30 inches as fencing. The May 2026 handout says a front yard fence needs a permit. So we do not promise a front yard height from the published text. We confirm it with the city for your lot, along with the sight triangle if you are on a corner. If the limit leaves you short of privacy, our guide to privacy when fence height is limited shows what still works.

What drawings and site-plan details does Southlake ask for?

The Fence Guidelines do not publish a drawing checklist. They say what needs a permit, what needs an engineer and what gets inspected, and they stop there. The closest published standard is the plot plan list in the city's residential accessory building guidelines, and the multi-purpose court checklist, which asks for the location of the fence, its height and its material.

From those documents, this is the package we prepare so the plans examiner has nothing to ask for. Plans are uploaded as PDF files, drawn to scale and labeled. The accessory guidelines state that scans of plans are not acceptable. Confirm the exact list for your project with a plans examiner before you upload.

  • Site plan on your survey: Street address, scale, north arrow, property lines, the house, driveway and sidewalk, and the fence line with its distance from the property lines.
  • Easements and drainage: Mark every easement and the direction of drainage, since the city's plot plan list asks for drainage arrows. Our guide to fences on utility easements explains what to look for on a plat.
  • Fence elevation: One typical panel showing height above grade, material, post spacing and, for iron, picket spacing.
  • Gates: Location, width and swing direction. Pool gates need the latch height shown.
  • Column and footing details: For brick or stone: column size and spacing, footing depth and the sealed engineered design where the 48-inch rule applies.
  • Pool barrier notes: Barrier height, clearance under the bottom rail and the largest opening, matched to the pool section of the guidelines.

How do I apply for a Southlake fence permit, step by step?

Everything is filed online. The Fence Guidelines say fence permits must be submitted online, and the city's Construction Information page says all permit submittals go through EnerGov Self-Service, the portal titled Southlake Building Inspections. The city states that contractors working in Southlake must register through the same system.

The guidelines do not give a review time for fences. The accessory building guidelines state a goal of completing plan reviews within ten working days once every submittal item is in and the review is paid. Whether that goal covers a fence permit is not stated, so ask when you apply. Fees are set in the city's Municipal Fee Schedule.

  1. Check the triggersCompare your design with both city lists above. Note height, columns, masonry, pool, front yard and floodplain.
  2. Get HOA approvalThe city tells owners to contact their association about covenants and deed restrictions. Settle the design there first.
  3. Prepare the drawingsSite plan, elevation, gate details and, for masonry, the engineer's sealed design.
  4. Create an account and applyIn the portal choose Login or Register, then Apply, and upload the drawings.
  5. Answer review commentsThe portal shows review status and comments. Upload corrections there.
  6. Build and call inspectionsRequest each inspection in the portal. Masonry gets a footing inspection before concrete. Every permitted fence gets a final.
Home screen of the City of Southlake Building Inspections online permit portal with the Apply and Request Inspection tiles outlined
The two tiles you will use: Apply to file the fence permit and upload drawings, Request Inspection once the work is ready. Screenshot: energov.cityofsouthlake.com, November 2026.

Can I build a modern horizontal fence in Southlake?

The zoning ordinance does not stop you. Section 39.2 lists acceptable materials, including natural and treated woods, masonry, and ornamental metal or wrought iron. It says nothing about which way the boards run. Corrugated metal panels are not permitted.

Three things can still change a horizontal design. First, the street behind you. Along arterials and collectors on the Master Thoroughfare Plan, Section 39.5 limits fences to masonry, ornamental metal or wrought iron, or stained cedar board-on-board with a cap and masonry columns no more than 14 feet apart, center to center. A horizontal slat fence is not on that list, so it would need the combination approval the ordinance leaves to the city's Administrative Official.

Second, a pool. Horizontal boards can work like a ladder, and the pool barrier section has its own rules for horizontal members, covered below. Third, your association, which may name the fence style. For how these fences are built, see our guide to horizontal wood fences and our cedar fencing page.

Horizontal cedar fence built on a cut-stone base
Horizontal cedar on a cut-stone base. In Southlake a masonry base or columns can bring the engineering and permit rules into play even when the wood above them would not. Photo: Park Cities Fence & Deck.

What do brick or stone columns add to the permit?

Columns put the fence on the permit list by themselves: the Fence Guidelines name fences that have brick or stone columns, with no height given. The accessory building guidelines repeat it: masonry fences and masonry columns for fences or gates need their own permit.

Engineering starts at 48 inches. Masonry fences or columns 48 inches or more from the bottom of the footing require a sealed engineered design. The measurement starts at the bottom of the footing, not at the lawn, so a column that looks modest above grade can still cross the line. The inspection list in the same document words it as "over 4 feet including footings". If your column is right at 4 feet, ask which wording the reviewer applies.

The footing inspection has an order to it. The design engineer or a representative inspects first and writes a letter of compliance. That letter is uploaded to the permit. Only then is the city's foundation inspection scheduled, and it happens before concrete is poured. We build brick and stone columns on engineered footings set below the clay movement zone, and our guide to masonry columns explains why the footing decides how long a column stays plumb.

Masonry columns along a fence line
Masonry columns along a fence line. In Southlake, columns like these need a permit, and a sealed engineered design once they measure 48 inches or more from the bottom of the footing. Photo: Park Cities Fence & Deck.

What does a pool barrier fence need in Southlake?

A permit, whatever its height. The city prints the barrier section of the 2021 International Swimming Pool and Spa Code inside its Fence Guidelines. The Pool Guidelines add that the barrier can ride on the pool permit if it is noted on the application and shown on the plans. Otherwise it needs a separate permit. Plaster does not go in until the permanent barrier is inspected and approved.

Our pool fencing is drawn to these numbers. For other cities, see pool fence rules by city.

  • Height: The top of the barrier is at least 48 inches above grade, measured on the side facing away from the pool.
  • Bottom gap: No more than 2 inches over grass or gravel, and no more than 4 inches over a solid surface such as concrete.
  • Openings: Nothing that lets a 4-inch sphere pass.
  • Horizontal members: The Southlake sheet says they must be a minimum of 45 inches apart. Where they are closer, the code puts them on the pool side and limits the gaps between vertical members to 1 3/4 inches.
  • Gates: Pedestrian gates open outward, away from the pool, and must take a locking device. A release reached from outside that is not self-locking sits at least 54 inches up at a residential pool.
  • Driveway gate in the barrier: An automatic vehicle gate that forms part of the barrier must close within two minutes of opening.

Does my HOA have to approve the fence, and what about subdivision walls and main roads?

The city's handout ends with a note to always contact your homeowners association about covenants and deed restrictions. Unlike Westlake, Southlake's fence documents do not say an HOA letter must be uploaded with the application. An association can set a tighter rule than the city, so we get its approval first. Our guide to HOA and deed restrictions shows how to read those documents.

Subdivision walls carry city rules of their own under Section 39.5. Where a perimeter screening wall stands between the subdivision and a public road, a new fence that runs along it or meets it may not be taller than that wall. Repairs and extensions must match its color, material or character. Where the developer or association built wrought iron or a similar open fence beside a thoroughfare, the ordinance does not allow a screening fence in the required side or rear yard parallel to it.

Then check the road. Fences along S.H. 114, F.M. 1709, F.M. 1938 (Davis Boulevard and Randol Mill Avenue) and the overlay portions of Carroll Avenue follow the Corridor Overlay District's architectural fencing rules. Other arterials and collectors get the material list described in the horizontal fence section. On those streets an ornamental iron fence or masonry is the design the ordinance names without conditions.

What if my design does not fit the rules?

The route is a variance from the Zoning Board of Adjustment. The Fence Guidelines send perimeter fences over 8 feet there. The application goes to the Planning department and asks for the specific provision you want varied and exactly how far your request differs from it.

The form is plain about what the board needs. You must show conditions unique to your property that make the standard rule unreasonable or unfair, that you did not create them, that your request is the minimum needed, and that it is not a special privilege. Four board members must vote in favor, and every owner's signature is notarized.

The city's 2026 schedule sets a submittal deadline, a staff review meeting and a payment and revisions deadline ahead of each hearing. Meetings are at Town Hall at 6:30 p.m., and none are scheduled in July. A granted variance authorizes a permit for one year unless the board sets another period. A redesign can avoid the hearing: move the tall section 10 feet inside the rear line, or drop the fence to 8 feet and add planting.

How does Southlake compare with Colleyville and Westlake, and how do we handle it?

Southlake's neighbors write very different rules. The Colleyville and Westlake columns below come from our Colleyville and Westlake pages, read from each city's code.

On a Southlake job, owner Jack Johnson comes out himself and checks the road, the subdivision wall, the pool and the easements before anything is drawn. We handle the permit, the HOA drawings and the 811 locate. For the paperwork in other cities, see fence permits, HOAs and utility locates in DFW. For a free written estimate, call (214) 755-8100 or send us your address.

Fence rules in Southlake, Colleyville and Westlake, as each city publishes them
TopicSouthlakeColleyvilleWestlake
When a permit is neededOver 7 feet, pool barriers, brick or stone columns, tall masonry; a city handout adds front yard, subdivision and floodplain fencesAny fence of permanent constructionTown lists a fence permit submittal; we did not read an exempt height
Tallest fence8 feet in a required yard; up to 14 feet when 10 feet inside the rear line8 feet in residential districts7 feet
Front yardNo separate height in Section 39; confirm with the cityPast the front of the house, fencing over 30 inches must be no more than 25 percent opaqueSolid fencing over 3.5 feet not allowed in front of the building setback line
Solid woodAllowed; limited along arterials and collectorsAllowed behind the front of the houseNot allowed
HOA letter with the applicationNot stated; the city says to contact your HOANot stated on our Colleyville pageOfficial approval letter required

What this means for you: A fence that passes in Southlake can fail one town over. A solid 8-foot cedar fence fits Southlake's general limit with a permit, needs a permit at any height in Colleyville and is not allowed in Westlake.

How Park Cities Fence & Deck helps

Jack Johnson comes out himself, looks at your property and gives you a free written estimate with a timeline. Wood, iron and masonry are all built in-house, so the advice fits the property. Related services: masonry fencing, pool fencing, wood fencing. We work in Southlake and Colleyville and across Dallas.

Call (214) 755-8100

Questions people ask next

Does a 6-foot wood privacy fence need a permit in Southlake?

Not by height. The Fence Guidelines start at over 7 feet. A 6-foot fence still needs a permit if it is part of a pool barrier or has brick or stone columns, and the city's May 2026 handout adds front yard, subdivision and floodplain fences. If none of those apply, confirm with Building Inspections at 817-748-8236 and check your HOA rules.

Can I apply for the Southlake fence permit myself as the homeowner?

The city has a Homeowner's Affidavit form that lists fence work. It is for an owner who lives at the address with a homestead exemption and will do the work personally, and it is notarized. If you later hire someone, the form says the Building Official must be told first so the contractor's registration can be verified.

What inspections does a Southlake fence permit get?

The Fence Guidelines list a Misc. Fence Final Inspection for fences, retaining walls and pool barriers. Engineered masonry also gets a footing inspection. The city says it makes every reasonable effort to inspect the same day when the request is in by 7:00 a.m.

Can I use chain link or barbed wire at a Southlake home?

Section 39.2 allows chain link only in the zoning districts it lists, which include AG, the SF-1, SF-2, SF-20 and SF-30 districts, RE-5 and RE-7. Barbed wire may not be placed on platted property zoned for single-family use. We do not install chain link. Our fences are cedar, ornamental iron and steel, and masonry.

Does replacing an old fence with the same fence need a permit?

The city's documents do not carve out replacements, so apply the same triggers to the new fence. Section 39.8 adds a rule for older fences built of materials no longer allowed: once repairs pass 50 percent of the fence length, or 100 linear feet combined, the whole fence must be replaced with approved materials.

Sources and further reading

General information, not legal advice. Rules change: we confirm the current requirements with your city or HOA before we build.